Week 6
10 May 2010
Monitor finish good utk line D5 klu2 ade problem..pastu kite org kne wat lifter bru untuk mini line hri 2..mini line tue pki 4 lifter..yg da siap 3 je n semua lifter dri thailand..jd kite org kene reka 1 lg lifter bru..made in sony pnye..xbeli dgn supplier..hri nie kiteorg abes kn wat lifter je n psg cyclinder kat lifter..gambr ade kat bwh..lifter made in sony..wat pki aluminium profile je..lifter nie pon pki concept graviti utk return pallet
11 May 2010
Hari nie psg valve dgn pnuematic system kat semua stopper, lifter dgn conveyor..pastu wat dressing bg nmpk kemas skit..pastu kitorg kne test run semua lifter and adjust speed setiap lifter..
12 May 2010
Ambik ukuran utk wat cover semua lifter..cover penting takut nnt operator cedera tangan tersepit kat lifter..sian dieorg nnt...da siap potong semua kiteorg kene pasang la semua cover 2..
13 - 14 May 2010
Wat alignment utk mini line dan mounting semua lifter..
15 May 2010
PIC utk finish good project line D7..